March 28
The pace seems to have slowed a bit, but things are clearly happening on the property.
1. They poured the cement for the sidewalk. (great but the steps are not very wide)
2. They installed the metal accent roof (looks great!)
3. Electrical, plumbing - significant progress
4. Granite countertops installed (they look so awesome!)
5. Installed the glasswork around the master BR shower (nice).
We still have no resolution on the tiling SNAFU. I'm a little worried they are thinking it will just go away. The Ryan folks have been understanding but no resolution after a week.
I continue to see items that are fine as is, but if given the option, I would have upgraded. I wish Ryan made some of these upgrades available at the beginning of the buying process. They would have made more money and we would be even happier. However, we knew this would be the case when we purchased, so no regrets or complaints - just suggestions for the future.
The front porch pillars, the floors/carpets, and the final
landscaping are the only major items remaining. We've noticed a few
issues and our project manager, Jason and his assistant Jeff, has been
terrific and responsive. It's great to work with a team that has
experience and integrity.
Some photos!





No comments:
Post a Comment